Join

Safety Improvements Underway on Old Bridge Road

LAKE RIDGE, Va. — Old Bridge Road will not be widened but it will be made safer.

Work is now underway along the four-lane commuter route that slows the commutes of many during the morning and afternoon rush hours.

The Virginia Department of Transportation has listed the following projects underway or completed as of this month:

Reduce run-off-road crashes at Colby Drive

-Reduce run-off-road accidents by adding “superelevation” and modifying adverse crown on the westbound lanes and Vertical Alignment Improvements at Colby Drive.

-Project was advertised for construction in Spring 2012. Construction has started and is scheduled to be completed in late 2012.

Improved Signal at Elysian Drive

-Improve signal visibility and upgrade traffic signal at Elysian Dr.

-Project was advertised for Construction in Spring 2012. Construction has been completed.

Upgraded pedestrian facilities at Clipper Drive

-Upgrade traffic signal, improve signal visibility and provide pedestrian accommodations at Clipper Drive.

-Project was advertised for Construction in Summer 2012. Construction to proceed in 2012.

Traffic signal at Occoquan Road

-Upgrade traffic signal at Occoquan Road.

-Project was advertised for Construction in July 2012. Construction is nearly completed.

Improvements at Antietam Road

-Install Signal Display for EB and WB approaches, Relocate Bus Stop Sign, provide ADA Ramp and sidewalk to Bus Stop, and provide Guardrail End Treatment at Antietam -Road project is currently under Design Phase. Construction advertisement is scheduled for mid 2014 (looking to accelerate under regional signal contract).

Signal, pedestrian improvements at Springwoods Drive

-Extend Left Turn Lane, Upgrade existing traffic signal to Mast Arm and Install Pedestrian Crossings at Springwoods Drive.

-Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014.

ADA ramps at Hedges Run Drive

-Upgrade existing Signal and install Pedestrian Crossings with ADA Ramps at Hedges Run Drive (design is being coordinated with County Sidewalk/ Superelevation project).

-Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014 (looking to accelerate under regional signal contract).

Improvements at Westridge Drive

-Upgrade Existing Traffic Signal and convert span wire signal support to mast arm mounts at Westridge Drive.

-Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014 (looking to accelerate under regional signal contract).

Turn lanes, ramps at Mohican Drive

-Upgrade Signal to Mast Arm Design, Install Ped. Crossings w. ADA Ramps; Construct/ Offset WB Left Turn Lane on Old Bridge Road at Mohican Drive (design is being coordinated with County Sidewalk/ Superelevation project).

-Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014.

Traffic signal at Smoketown Road

-Upgrade existing traffic signal from Span Wire to Mast Arm at Smoketown Rd.

-Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014 (looking to accelerate under regional signal contract).

Sidewalk from Hedges Run to Festival at Old Bridge

-Construct sidewalk and improve the cross section to provide more “superelevation” on north side of Old Bridge Road, from Hedges Run toDillingham Square/Cricket Lane.

-VDOT Safety project was combined with County sidewalk project for improved coordination and accelerated construction. Project scheduled to be advertised for construction fall 2012.

Visibility improvements at Harbor Drive

-Offset left turn lanes to improve sight distance and signal visibility at Harbor Drive.

-Project was advertised for construction in Spring 2012. Construction has started and is scheduled to be completed in spring 2013.

Sidewalk between Titania and Cricket lanes

-Construct sidewalk, handicap ramps, crosswalks, and install pedestrian signals at specific intersections from Titania to Cricket Lane

-Project was advertised for construction in October 2011. Construction has been completed.

Drivers should expect to see orange cones in the area for the foreseeable future as these projects continue, and most of the daytime work will take place between 9 a.m. and 3 p.m. to avoid the height of the rush hour periods, said Prince William Occoquan District Supervisor Mike May.

May said commuters have called him to report instances of slow traffic, and at least one instance where construction crews forgot to remove equipment from the road.

More from may in a emailed statement to his constituents:

“When completed, these projects should improve safety and promote better traffic flow along Old Bridge. However, in the meantime, you will see construction equipment and activity and it will have some impact on travel conditions from time to time.”

“In fact, about two weeks ago on Friday afternoon at about 5:00 p.m., my office received a phone call from a concerned constituent who mentioned that VDOT had forgotten to remove the barriers from the construction project between Rolling Brook and Harbor before rush hour began.”

“As a result, we alerted the county police and officers were immediately dispatched to move the barriers in order to increase the flow of traffic. Unfortunately, as many of you commuting that day probably realized, the traffic situation had already become a disaster,” stated May. 

 

Author

Recent Stories

The Manassas City Council voted to extend a lucrative tax incentive for Micron Technology Inc. through 2035, solidifying the semiconductor company’s continued presence in the city. The deal, passed during the February 10, 2025, council meeting, ensures Micron’s annual tax payments increase by 4% while maintaining a lower tax rate than other manufacturers.

However, the decision has raised questions about a potential conflict of interest involving Mayor Michelle Davis-Younger. Multiple sources have indicated that Davis-Younger is in a relationship with Delbert Parks, Vice President and Site Director at Micron’s Manassas facility.

Parks is named in an official letter from the mayor, dated the same day as the vote, outlining the incentives offered to Micron. During the meeting, Vice Mayor Mark Wolfe alluded to the relationship, stating that “some of the comments floating around online are BS,” referring to speculation that the mayor’s ties to Parks influenced the tax break discussions.

The Prince William Board of County Supervisors has approved a 24-acre rezoning for a new data center development along Wellington Road, despite opposition from Supervisor Bob Weir and concerns about its proximity to Unity Reed High School.

On February 4, 2025, the board approved Rezoning #REZ2024-00042, NVA05C, changing the property’s zoning from agricultural and business districts to Planned Business District (PBD) to accommodate a data center. The site, located 700 feet southwest of Freedom Center Boulevard and Wellington Road, is part of Innovation Park, an area designated for high-tech development.

The rezoning application was submitted by STACK Infrastructure, which operates data centers in multiple locations across North America, EMEA, and Asia Pacific. Some key Northern Virginia locations include:  Manassas, Ashburn, and Leesburg.

Fredericksburg is taking another step forward to become a more walkable community with the recent start of construction off LaFayette Boulevard, which is part of the city’s Twin Lake Drive and Kensington Pedestrian Connector project.

This $2.4 million project includes extending a 10-foot wide paved shared-use path along the north side of Lafayette Boulevard between Twin Lake Drive and St. Paul Street in the City of Fredericksburg. The path will be accessible, with ramps and crosswalks built where the route intersects with Twin Lakes Drive, Springwood Drive, Kensington Place, and St. Paul Street.

The project includes a paved access point to the Virginia Central Railway Trail from the cul-de-sac of Springwood Drive, and a bike repair station will be installed at Alum Spring Park.

The process Fredericksburg City Council is following to fill the vacant Ward 3 seat could conflict with state code—especially with a provision added last year that states that governing bodies must publicly announce the names of those being considered to fill a vacant seat at least seven days before the appointment is made.

? A Night on the Riviera

Experience a magical evening at the Embassy of France with A Night on the Riviera, an event that will transport you to the glamour of the French Riviera while celebrating the vibrant spirit of Mardi Gras! ?

?? Indulge in an exquisite selection of French wines and champagne, paired with the finest French cuisine prepared by the talented Chef of the Embassy of France. Additionally, Chef Hugh Cossard will be carving ham live, ensuring freshness and exceptional flavor. Don’t miss out on the authentic French crêpes, made to order and sure to transport you straight to the streets of Nice.

Read More

Submit your own Community Post here.

Travel to French soil and join us for a night filled with two of the most beloved French traditions—no plane ticket required! ?

On January 25th, we invite you to experience the magic of Galette des Rois, a 700-year-old tradition celebrated across France throughout the entire month of January (and even beyond!). This sweet, almond-filled puff pastry topped with a golden crown isn’t just a treat—it’s a celebration! The lucky person who finds the fève (a porcelain charm hidden in one of the slices) becomes the King or Queen for the Day, and don’t worry—there will be plenty of royalty to go around! ??

But that’s not all! In France, Les Voeux (New Year’s wishes) continue throughout January, often accompanied by Champagne and good cheer. We’re bringing that festive spirit to you, with a lively evening packed with French food, wine, and music.

What’s in store:

Read More

Submit your own Community Post here.

Ă—

Subscribe to our mailing list