News

Brooke Road to be closed until late September

STAFFORD — The date for reopening Brooke Road to through traffic near Stagecoach Road has been moved to late September due to unforeseen problems.

Brooke Road was closed to through traffic on September 17, 2018.

Record-setting rainfalls impacted the progress of construction and led to an earlier delay.

The delay to September is due to two unexpected factors discovered during construction.

First, materials being used in the wetlands area were not performing satisfactorily. County staff, the Virginia Department of Transportation (VDOT), and the contractor had to work together to find a substitute.

They then had to submit and receive VDOT approvals.

Second, the plan for relocating Dominion lines needed to change, which meant obtaining additional utility easements.

Enhancements to Brooke Road include horizontal and vertical realignment, lane and shoulder widening, and sight distance improvements.

The road closure is necessary to extend box culverts located beneath the road and install piling between the culverts.

The project calls for modifications to road grades and curvature to enhance safety.

All residents living within the construction area will continue to be able to reach their property throughout the project.

More information may be found about the Brooke Road Safety Improvement Project on Stafford’s website.